Skip to content

9706 · 4.1.1

Activity Based Costing — practice questions

Practice and worked examples for 9706 Activity Based Costing. Short previews only — attempt the full question in MarkScheme against the official scheme.

Worked example 1

Component Co manufactures two components, C1 and C2. The company is considering adopting an Activity Based Costing system. The following data is available:

C1C2
Production units2,0005,000
---------
Direct material cost per unit$25$30
Direct labour cost per unit$15$10

Total production overheads are $188,000, which are analysed as follows:

Activity Cost PoolCost ($)Cost Driver
Machining80,000Machine hours
---------
Set-ups48,000Number of production runs
Material handling60,000Number of material requisitions

The activities for each component are:

C1C2
Machine hours per unit2.01.2
---------
Number of production runs4080
Number of material requisitions6090

Required: Calculate the full cost per unit for components C1 and C2 using Activity Based Costing.

Show solution outline

Step 1: Calculate Total Activity for Each Cost Driver

  • Total Machine Hours:
    • C1: 2,000 units × 2.0 hours/unit = 4,000 hours
    • C2: 5,000 units × 1.2 hours/unit = 6,000 hours
    • Total: 4,000 + 6,000 = 10,000 machine hours
  • Total Production Runs: 40 + 80 = 120 runs
  • Total Material Requisitions: 60 + 90 = 150 requisitions

Step 2: Calculate Cost Driver Rates

  • Machining Rate: $80,00010,000 machine hours=$8.00 per machine hour\frac{\text{\textdollar}80,000}{10,000 \text{ machine hours}} = \text{\textdollar}8.00 \text{ per machine hour}
  • Set-up Rate: $48,000120 production runs=$400 per run\frac{\text{\textdollar}48,000}{120 \text{ production runs}} = \text{\textdollar}400 \text{ per run}
  • Material Handling Rate: $60,000150 requisitions=$400 per requisition\frac{\text{\textdollar}60,000}{150 \text{ requisitions}} = \text{\textdollar}400 \text{ per requisition}

Step 3: Allocate Overhead Costs to Products

For Component C1:

  • Machining: 4,000 hours × $8.00/hour = $32,000
  • Set-ups: 40 runs × $400/run = $16,000
  • Material Handling: 60 requisitions × $400/requisition = $24,000
  • Total Overhead for C1: $32,000 + $16,000 + $24,000 = $72,000

For Component C2:

  • Machining: 6,000 hours × $8.00/hour = $48,000
  • Set-ups: 80 runs × $400/run = $32,000
  • Material Handling: 90 requisitions × $400/requisition = $36,000
  • Total Overhead for C2: $48,000 + $32,000 + $36,000 = $116,000 (Check: $72,000 + $116,000 = $188,000, which matches total overheads)

Step 4: Calculate Full Cost Per Unit

For Component C1:

  • Direct Costs per unit: $25 (material) + $15 (labour) = $40.00
  • Overhead per unit: $72,0002,000 units=$36.00\frac{\text{\textdollar}72,000}{2,000 \text{ units}} = \text{\textdollar}36.00
  • Full Cost per unit (C1): $40.00 + $36.00 = $76.00

For Component C2:

  • Direct Costs per unit: $30 (material) + $10 (labour) = $40.00
  • Overhead per unit: $116,0005,000 units=$23.20\frac{\text{\textdollar}116,000}{5,000 \text{ units}} = \text{\textdollar}23.20
  • Full Cost per unit (C2): $40.00 + $23.20 = $63.20

Worked example 2

Deluxe Gadgets Ltd produces two products: a Standard model and a Premium model. Total overheads are $150,000. The company currently uses direct labour hours to absorb overheads. Total direct labour hours are 10,000.

Product Data:

StandardPremium
Annual Production (units)8,0002,000
---------
Direct Cost per unit$30$50
Direct Labour Hours per unit1.01.0

Management is considering ABC. Overheads have been analysed:

ActivityCost ($)Cost DriverStandardPremium
Machining80,000Machine Hours4,0002,000
---------------
Quality Control70,000No. of Inspections150200

Required: (a) Calculate the overhead cost per unit for each product using the traditional method (direct labour hours). (b) Calculate the full cost per unit for each product using ABC. (c) Comment on the difference in the unit costs.

Show solution outline

(a) Traditional Absorption Costing

Step 1: Calculate Overhead Absorption Rate (OAR)

  • Total Direct Labour Hours = (8,000 units × 1.0 hr) + (2,000 units × 1.0 hr) = 10,000 hours
  • OAR = Total OverheadsTotal Direct Labour Hours=$150,00010,000 hours=$15 per direct labour hour\frac{\text{Total Overheads}}{\text{Total Direct Labour Hours}} = \frac{\text{\textdollar}150,000}{10,000 \text{ hours}} = \text{\textdollar}15 \text{ per direct labour hour}

Step 2: Calculate Overhead Cost per Unit

  • Standard: 1.0 DLH/unit × $15/DLH = $15.00
  • Premium: 1.0 DLH/unit × $15/DLH = $15.00

(b) Activity Based Costing

Step 1: Calculate Cost Driver Rates

  • Total Machine Hours = 4,000 + 2,000 = 6,000 hours
  • Total Inspections = 150 + 200 = 350 inspections
  • Machining Rate: $80,0006,000 hours=$13.33 per machine hour\frac{\text{\textdollar}80,000}{6,000 \text{ hours}} = \text{\textdollar}13.33 \text{ per machine hour}
  • Quality Control Rate: $70,000350 inspections=$200 per inspection\frac{\text{\textdollar}70,000}{350 \text{ inspections}} = \text{\textdollar}200 \text{ per inspection}

Step 2: Allocate Overheads and Calculate Full Unit Cost For Standard Model (8,000 units):

  • Machining: 4,000 MH × $13.33/MH = $53,320
  • Quality Control: 150 inspections × $200/inspection = $30,000
  • Total Overhead = $53,320 + $30,000 = $83,320
  • Overhead per unit = $83,3208,000 units=$10.42\frac{\text{\textdollar}83,320}{8,000 \text{ units}} = \text{\textdollar}10.42
  • Full Cost per unit: $30 (Direct) + $10.42 (Overhead) = $40.42

For Premium Model (2,000 units):

  • Machining: 2,000 MH × $13.33/MH = $26,660
  • Quality Control: 200 inspections × $200/inspection = $40,000
  • Total Overhead = $26,660 + $40,000 = $66,660
  • Overhead per unit = $66,6602,000 units=$33.33\frac{\text{\textdollar}66,660}{2,000 \text{ units}} = \text{\textdollar}33.33
  • Full Cost per unit: $50 (Direct) + $33.33 (Overhead) = $83.33 (Note: Total ABC overheads = $83,320 + $66,660 = $149,980. The small difference from $150,000 is due to rounding the machining rate.)

(c) Commentary

The traditional method allocated an equal overhead cost ($15.00) to both products because they use the same number of direct labour hours. This under-costs the complex Premium model and over-costs the simpler Standard model.

ABC reveals that the Premium model is significantly more expensive to produce ($83.33 vs. traditional full cost of $65). This is because it consumes a disproportionately high amount of the expensive quality control activity (200 of 350 inspections for only 20% of the units). Pricing based on the traditional cost would likely lead to the Premium model being sold at a loss or a very low margin.