Worked example 1
Component Co manufactures two components, C1 and C2. The company is considering adopting an Activity Based Costing system. The following data is available:
| C1 | C2 | |
|---|---|---|
| Production units | 2,000 | 5,000 |
| --- | --- | --- |
| Direct material cost per unit | $25 | $30 |
| Direct labour cost per unit | $15 | $10 |
Total production overheads are $188,000, which are analysed as follows:
| Activity Cost Pool | Cost ($) | Cost Driver |
|---|---|---|
| Machining | 80,000 | Machine hours |
| --- | --- | --- |
| Set-ups | 48,000 | Number of production runs |
| Material handling | 60,000 | Number of material requisitions |
The activities for each component are:
| C1 | C2 | |
|---|---|---|
| Machine hours per unit | 2.0 | 1.2 |
| --- | --- | --- |
| Number of production runs | 40 | 80 |
| Number of material requisitions | 60 | 90 |
Required: Calculate the full cost per unit for components C1 and C2 using Activity Based Costing.
Show solution outline
Step 1: Calculate Total Activity for Each Cost Driver
- Total Machine Hours:
- C1: 2,000 units × 2.0 hours/unit = 4,000 hours
- C2: 5,000 units × 1.2 hours/unit = 6,000 hours
- Total: 4,000 + 6,000 = 10,000 machine hours
- Total Production Runs: 40 + 80 = 120 runs
- Total Material Requisitions: 60 + 90 = 150 requisitions
Step 2: Calculate Cost Driver Rates
- Machining Rate:
- Set-up Rate:
- Material Handling Rate:
Step 3: Allocate Overhead Costs to Products
For Component C1:
- Machining: 4,000 hours × $8.00/hour = $32,000
- Set-ups: 40 runs × $400/run = $16,000
- Material Handling: 60 requisitions × $400/requisition = $24,000
- Total Overhead for C1: $32,000 + $16,000 + $24,000 = $72,000
For Component C2:
- Machining: 6,000 hours × $8.00/hour = $48,000
- Set-ups: 80 runs × $400/run = $32,000
- Material Handling: 90 requisitions × $400/requisition = $36,000
- Total Overhead for C2: $48,000 + $32,000 + $36,000 = $116,000 (Check: $72,000 + $116,000 = $188,000, which matches total overheads)
Step 4: Calculate Full Cost Per Unit
For Component C1:
- Direct Costs per unit: $25 (material) + $15 (labour) = $40.00
- Overhead per unit:
- Full Cost per unit (C1): $40.00 + $36.00 = $76.00
For Component C2:
- Direct Costs per unit: $30 (material) + $10 (labour) = $40.00
- Overhead per unit:
- Full Cost per unit (C2): $40.00 + $23.20 = $63.20