Worked example 1
A builder contracts to install a central heating system for £5,600. The work is completed, but the system emits fumes and does not heat the house properly. A heating engineer quotes £1,700 to fix the issues. The homeowner refuses to pay the builder anything. Advise the builder.
Show solution outline
- Identify the Contract Type: This is an entire contract for a single lump sum (£5,600) for a complete installation.
- Assess Performance: The issue is whether performance is substantial. The defects are serious: the system doesn't heat the house (its main purpose) and is unsafe (emits fumes). This is analogous to Bolton v Mahadeva.
- Apply the 'Substantial Performance' Test: The court considers two factors: the nature of the defect and the cost of cure relative to the contract price.
- Nature of Defect: The defects go to the root of the contract; the system fails its primary purpose.
- Cost of Cure: The cost to fix is £1,700. We calculate this as a percentage of the contract price:
- Calculation: (£1,700 / £5,600) * 100% = 30.4%
- Compare to Case Law: In Bolton v Mahadeva, the cost of cure was approx. 30% of the contract price (£174 / £560), and performance was held NOT to be substantial. The facts here are very similar.
- Conclusion: Performance is not substantial. The builder has breached the contract by failing to provide what was promised. Under the strict rule for entire contracts, the builder is not entitled to any payment. The homeowner is correct to refuse payment.