Operations planning flashcards

Revision flashcards for Cambridge 9609 Operations planning (syllabus 9.3.5). Flip, recall, then mark a real past-paper question.

  • Card

    Operations planning chain?

    Forecast → MPS → MRP → purchase/production orders.

  • Card

    Master production schedule?

    States what finished products to make and when.

  • Card

    MRP?

    Uses BOM + MPS to calculate raw material/component needs.

  • Card

    Bill of materials (BOM)?

    List of components per finished product — MRP input.

  • Card

    Forecast error impact?

    Over-forecast → excess stock; under → stock-outs (8.1.3).

  • Card

    ERP link?

    ERP automates MPS/MRP with live inventory (9.3.3).

  • Card

    Rolling schedule?

    Plan updated regularly as new demand data arrives.

  • Card

    Capacity check?

    MPS must fit available capacity — link 4.3.1.

  • Card

    What is a Master Production Schedule (MPS)?

    A detailed plan that states which end products are required, how many are needed, and when they need to be produced. It links demand forecasts to specific production activities, considering capacity and inventory.

  • Card

    What are the three key inputs for an MRP I system?

    1. The Master Production Schedule (MPS). 2. The Bill of Materials (BOM). 3. The Inventory Records File (IRF).

  • Card

    Define 'Bill of Materials' (BOM).

    A comprehensive, structured list of all the raw materials, components, and sub-assemblies required to produce one unit of a finished product. It is essential for MRP calculations.

  • Card

    What is the primary purpose of demand forecasting in operations?

    To predict future customer demand for products, enabling a business to plan production levels, manage inventory, and allocate resources effectively to meet that demand without excessive waste or stock-outs.

  • Card

    How does MRP II (Manufacturing Resource Planning) differ from MRP I?

    MRP II expands on MRP I by integrating all manufacturing resources, including finance (budgets), marketing (sales data), and HR (labour planning), into the planning process. It is a business-wide system, not just a materials control tool.