Skip to content

9609 · 9.3.5

Operations planning — practice questions

Practice and worked examples for 9609 Operations planning. Short previews only — attempt the full question in MarkScheme against the official scheme.

Worked example 1

Furniture maker forecasts 500 tables in March. MPS set accordingly. MRP orders 2,000 table legs (4 per table). Actual sales 350. Explain consequences and improvements.

Show solution outline

Over-forecast 30%: 150 excess tables if produced — inventory waste (9.3.4), cash tied up (5.1.2).

MRP consequence: 600 excess legs ordered if production started — supplier penalties or storage costs.

Fixes: Rolling 4-week MPS updated from actual orders not annual average; ERP for real-time sales feed (9.3.3).

Capacity: Before locking MPS, check labour hours vs 4.3.1 utilisation — don't plan beyond max capacity.

Worked example 2

A-Star Electronics forecasts demand for 120 units of its 'Galaxy Tablet' for Week 8. The company has 20 tablets in finished goods inventory and wants to maintain a safety stock of 10 units. The Bill of Materials (BOM) for one tablet requires 1 Screen Assembly (SA) and 2 Battery Packs (BP). Current component inventory is 30 Screen Assemblies and 50 Battery Packs. Lead times are 2 weeks for SA and 1 week for BP. Production of a batch of tablets takes 1 week. Calculate the required production run for the MPS and the net requirements and order timing for each component.

Show solution outline

This example demonstrates the full operations planning process from forecast to component ordering.

Step 1: Determine the Master Production Schedule (MPS) Quantity The MPS defines how many finished goods to produce. This is based on the forecast, existing stock, and safety stock targets.

  • Formula: MPS Quantity = (Forecast Demand + Safety Stock) - On-Hand Inventory
  • Calculation: (120 units + 10 units) - 20 units = 110 tablets
  • The MPS will schedule the production of 110 tablets, to be completed by Week 8.

Step 2: Calculate Gross Component Requirements This is the total number of components needed to produce the 110 tablets from the MPS.

  • Screen Assembly (SA): 110 tablets × 1 SA/tablet = 110 Screen Assemblies
  • Battery Pack (BP): 110 tablets × 2 BPs/tablet = 220 Battery Packs

Step 3: Calculate Net Component Requirements This is the quantity to order after using existing component stock.

  • Formula: Net Requirement = Gross Requirement - On-Hand Inventory
  • Screen Assembly (SA): 110 (Gross) - 30 (On-Hand) = 80 units
  • Battery Pack (BP): 220 (Gross) - 50 (On-Hand) = 170 units

Step 4: Plan Order Placement (Time-Phasing) Orders must be placed so components arrive before production begins. Since production takes 1 week and must finish by Week 8, it must start in Week 7. Therefore, components are needed by the start of Week 7.

  • Formula: Order Week = Required Week - Lead Time
  • Screen Assembly (SA): Required by Week 7. Lead Time is 2 weeks. Order must be placed in Week 5 (Week 7 - 2).
  • Battery Pack (BP): Required by Week 7. Lead Time is 1 week. Order must be placed in Week 6 (Week 7 - 1).

Conclusion: A-Star must order 80 Screen Assemblies in Week 5 and 170 Battery Packs in Week 6 to meet its production plan.