Worked example 1
Engineering firm wins defence contract needing multidisciplinary teams (engineers, procurement, legal) for 18 months while maintaining functional departments. Recommend a structure.
Show solution outline
Pure functional: Departments slow to integrate for contract — silo problem.
Pure project: Loses functional expertise depth when contract ends.
Matrix recommended: Engineers report to engineering head and project manager — flexible staffing across contract life.
Cost: Dual meetings, role ambiguity — needs strong 7.2 communication and 7.1.4 trust.